After repeated phone calls from residents and businesses who were left in the dark, the City Council has opened this docket to investigate the root causes of these outages and will be requiring Entergy to implement a plan to fix the problem.
Entergy’s own data shows that 98% of all outages since 2011 have been caused by problems with the transmission and distribution system.
Check out these Watchdog blogs to learn more about the causes of the outages, how they hinder the New Orleans Community, Entergy’s attempts to reduce outages, and how the City Council decided to hold Entergy accountable for its “inaction and omissions in mitigating” the thousands of power outages the city experiences every year:
2024 01 15 UD-17-04 ADV Motion to Modify Procedural Schedule
2019 04 25 UD-17-04 ADV Comments on ENO’s Re. ENO Filing in Prudence Investigation
2019 04 11 UD-17-04 ADV Motion to Modify Procedural Schedule
2019 04 11 UD-17-04 ADV Motion to Modify Procedural Schedule CL
2019 03 14 UD-17-04 ADV Unopposed Motion to Extend Dates in Procedural Schedule
2019 03 14 UD-17-04 ADV Unopposed Motion to Extend Dates in Procedural Schedule CL
2019 03 14 UD-17-04 ADV Order Approving Motion to Extend Dates
2019 02 18 UD-17-04 ADV Comments on 2019 Remediation Plan
2019 02 18 UD-17-04 ADV Comments on 2019 Remediation Plan Exhibit 1
2019 02 18 UD-17-04 ADV Comments on 2019 Remediation Plan CL
2018 12 28 UD-17-04 ADV Comments on ENO 2018 Project Status Report
2018 12 28 UD-17-04 ADV Comments on ENO 2018 Project Status Report Cover
2018 11 16 UD-17-04 Advisors Unopposed Motion to Reset Dates in Procedural Schedule
2018 11 08 UD-17-04 Advisors Motion to Continue Date to Convene Status Conference Call
2018 11 08 UD-17-04 Advisors Motion to Continue Date to Convene Status Conference Call CL
2017 11 01 UD-17-04 Advisor’s Initial Report corrected
2017 11 01 UD-17-04 Advisor’s Initial Report cover and attachment corrected
2024 03 05 UD-17-04 CURO Updated Service List.docx
2024 02 08 UD-17-04 CURO Updated Service List.docx
2024 02 07 UD-17-04 CURO Updated Service List.docx
2024 01 16 UD-17-04 CNO Order Approving Motion to Modify Procedural Schedule
2023 08 17 UD-17-04 CNO R-23-348 Extending Supplemental Procedural Schedule
2023 07 07 UD-17-04 CURO Updated Service List.docx
2023 06 15 UD-17-04 ENO 1st Qtr Reliability Plan Status Report
2023 06 07 UD-17-04 CNO R-23-150 Establishing Supplemental Procedural Schedule
2023 05 24 UD-17-04 CURO Updated Service List.docx
2023 04 24 UD-17-04 CURO R-23-15 Re-opening Docket
2023 04 17 UD-17-04 CURO Updated Service List.docx
2023 02 16 UD-17-04 CNO R-23-73 Implementing Electric System Distribution Reliability Standards
2023 01 10 UD-17-04 CURO Updated Service List.docx
2022 08 18 UD-17-04 CURO R-22-372 Proposed Distribution Reliability Standards
2022 08 18 UD-17-04 CURO Updated Service List.docx
2022 08 12 UD-17-04 CURO Approved Late Intervention
2022 06 21 UD-17-04 CURO Updated Service List.docx
2019 11 07 UD-17-04 CNO R-19-442 Imposing $1M Reliability Fine
2019 10 22 UD-17-04 CNO Prudence Resolution DRAFT
2019 08 09 UD-17-04 CNO Judge Gulin Order & Admin Record Chart
2019 08 08 UD-17-04 CNO Final Evidentiary and Administrative Record Chart
2019 07 12 UD-17-04 CNO Order Extending Date to Certify the Record
2019 07 09 UD-17-04 CNO Updated Service List
2019 06 10 UD-17-04 City Council Order
2019 05 20 UD-17-04 CNO Order extending schedule
2019 05 06 UD-17-04 CNO Updated Service List
2019 04 12 UD-17-04 CNO Granting ADV Motion to Modify Procedural Schedule.pdf
2019 03 29 UD-17-04 CNO Updated Service List
2019 03 15 UD-17-04 CNO Order Granting Motion to Extend
2018 11 19 UD-17-04 CNO Order to reset Schedule for 2018 Remediation Plan & Progress Report
2018 11 16 UD-17-04 CNO Revised Service List
2018 11 12 UD-17-04 CNO R-18-475 Prudence Investigation Re. Electric service Disruptions
2018 11 09 UD-17-04 CNO Order to Continue Date for Status Conference
2018 09 10 UD-17-04 CNO Order to Modify Schedule
2018 09 05 UD-17-04 CNO Advisors Amended Schedule
2018 09 04 UD-17-04 CNO Advisors Unopposed Motion to Amend Procedural Schedule
2018 06 12 UD-17-04 CNO Service List
2018 05 07 UD-17-04 CNO Order of Revised Procedural Schedule
2018 04 18 UD-17-04 CNO Updated Service List
2018 03 12 UD-17-04 CNO Updated Service List
2017 10 10 UD-17-04 CNO Order Re. Objections to GSREIA Intervention
2017 09 12 UD-17-04 CNO Order Granting LRP Motion to Dismiss Petition for Intervention
2017 09 11 UD-17-04 Technical Advisors Review of ENO’s Outages and Reliability Performance
2017 09 08 UD-17-04 CNO Service List
2017 09 08 UD-17-04 CNO Order establishing schedule to LRP’s pending Request to Intervene
2017 08 10 UD-17-04 CNO Corrected R-17-427 Reliability Performance Standards
2023 11 30 UD-17-04 ENO 3rd Qtr Customer Interruptions Report
2023 11 30 UD-17-04 ENO 3rd Qtr Reliability Plan Status Report
2023 09 07 UD-17-04 ENO 2nd Qtr Customer Interruptions Report
2023 09 07 UD-17-04 ENO 1st Qtr Reliability Plan Status Report
2023 06 15 UD-17-04 ENO 1st Qtr Customer Interruptions Report
2023 04 19 UD-17-04 ENO Letter to Councilmembers Re. $1M Reliability Fine
2023 04 14 UD-17-04 ENO Compliance Submission Re. R-23-73 (Public)
2023 03 31 UD-17-04 ENO 4th Qtr Customer Interruptions Report
2023 03 31 UD-17-04 ENO 4th Qtr Reliability Plan Progress Report
2022 12 02 UD-17-04 ENO 3rd Qtr Customer Interruptions Report
2022 12 06 UD-17-04 ENO 3rd Qtr Reliability Plan Progress Report
2022 09 16 UD-17-04 ENO Comments Re. Minimum Standards & Penalties
2022 08 22 UD-17-04 & UD-08-02 ENO Energy Smart Midyear Report PY 12
2022 08 04 UD-17-04 ENO 2nd Qtr Reliability Plan Progress Report
2022 07 28 UD-17-04 ENO 2nd Qtr Customer Interruptions Report YTD June
2022 07 28 UD-17-04 ENO 2nd Qtr Customer Interruptions Analysis YTD June.xlsx
2022 06 17 UD-17-04 ENO 2022 Reliability Plan & 1st Qrt Progress Report
2022 05 19 UD-17-04 ENO 1st Qtr Customer Interuptions Analysis (1/1/22 – 3/3/122).xlsx
2022 05 19 UD-17-04 ENO 1st Qtr Customer Interruptions Report
2022 03 29 UD-17-04 ENO 4th Quarter Reliability Progress Report
2022 03 24 UD-17-04 ENO Customer Interruptions Analysis.xlsx
2022 03 24 UD-17-04 ENO 4th Quarter Customer Interruptions Report
2021 12 15 UD-17-04 ENO Reliability Progress Report – September 2021
2021 12 15 UD-17-04 ENO 3rd Quarter Customer Interruptions Report
2021 09 29 UD-17-04 ENO Report Customer Interruptions 2nd Quarter Re. R-17-427
2021 09 29 UD-17-04 ENO Reliability Progress Report Thru June 2021
2021 08 23 UD-17-04 ENO Reliability Plan ’21
2021 08 23 UD-17-04 ENO CI Report ’20
2021 08 23 UD-17-04 ENO CI Analysis ’20 Attachment.xlsx
2021 03 31 UD-17-04 ENO Reliability Project Status Report YTD Dec 2020
2020 12 14 UD-17-04 ENO Reliability Progress Report Oct
2020 12 14 UD-17-04 ENO CI Report YTD October
2020 12 14 UD-17-04 ENO CI Analysis YTD October
2020 10 22 UD-17-04 ENO Bi-Mthly CI Rpt YTD Aug Attachment
2020 10 22 UD-17-04 ENO Bi-Mthly CI Rpt YTD Aug
2020 10 22 UD-17-04 ENO Reliability Project Status Rpt-Aug
2020 08 06 UD-17-04 ENO Customer Interruptions Rpt YTD June (CI Analysis)
2020 08 06 UD-17-04 ENO Customer Interruptions Rpt YTD June
2020 08 03 UD-17-04 ENO Customer Interruptions Rpt YTD April (CI Analysis)
2020 08 03 UD-17-04 ENO Customer Interruptions Rpt YTD April
2020 07 30 UD-17-04 ENO Customer Interruptions Report YTD Feb
2020 07 30 UD-17-04 ENO Reliability Plan Project Status Rpt-June
2020 07 30 UD-17-04 ENO Reliability Plan Project Status Rpt-Apr
2020 07 29 UD-17-04 ENO 2020 Reliability Plan Project Status Rpt-Feb
2020 07 17 UD-17-04 ENO 2020 Reliability Plan (FINAL)
2020 07 03 UD-17-04 ENO CI Analysis YTD Feb
2020 06 22 UD-17-04 ENO Ltr & Final Rpt on 2019 Reliability Plan (FINAL)
2020 01 31 UD-17-04 ENO Bi-Monthly Report on Customer Outages Oct – Nov 2019
2020 01 31 UD-17-04 ENO Bi-Monthly Report Outage Cause Analysis Oct – Nov 2019
2019 12 17 UD-17-04 ENO Reliabilty Project Status Report as of 10/31/19
2019 11 27 UD-17-04 ENO Bi-Monthly Report on Customer Outages for 8/1/19 – 9/30/19
2019 11 27 UD-17-04 ENO Bi-Monthly Report Outage Cause Analysis 8/1/19 – 9/30/19
2019 10 01 UD-17-04 ENO Bi-Monthly Reliability Filing June 1, 2019 – July 31, 2019
2019 07 31 UD-17-04 ENO Bi-Monthly Report on Customer Outages for April 1, 2019 – May 31, 2019
2019 07 31 UD-17-04 ENO Bi-Monthly Report on Customer Outages for 4/1/19 through 5/31/19 CL
2019 06 28 UD-17-04 ENO Rebuttal Comments
2019 06 28 UD-17-04 ENO Exhibit MPS-2B Reliability Capital
2019 06 28 UD-17-04 ENO Exhibit MPS-2A Reliability Capital
2019 06 07 UD-17-04 ENO Motion for Extension of Time to File Rebuttal Comments and Testimony
2019 05 30 UD-17-04 ENO Bi-Monthly Report on Customer Outages for 2/1/19-3/31/19 Att. Chart
2019 05 30 UD-17-04 ENO Bi-Monthly Report on Customer Outages for 2/1/19-3/31/19 CL
2019 05 24 UD-17-04 ENO Notice of Deposition of Joseph W. Rogers
2019 04 03 UD-17-04 ENO Bi-Monthly Graph Outages by Cause
2019 04 03 UD-17-04 ENO Bi-Monthly Filing Requirement CL & CD
2019 04 01 UD-17-04 ENO Bi-Monthly Reliability Project Report
2019 03 08 UD-17-04 ENO Re. S&WB & CNOADV Comments on Reliability Plan
2019 03 07 UD-17-04 ENO R-17-427 Bi-Monthly Report on Customer Outages
2019 01 31 UD-17-04 ENO 2018 Reliability Project Status Report
2019 01 18 UD-17-04 ENO 2019 Reliability Plan
2019 01 11 UD-17-04 ENO Re. AAE & ADV Comments
2019 01 10 UD-17-04 ENO Re. Prudence Investigation
2018 12 31 UD-17-04 ENO letter re. Year End 2018 Reliability Project Status
2018 12 27 UD-17-04 ENO Re. Intervenors’ & Advisors’ Comments on Quanta Technology Report
2018 11 30 UD-17-04 ENO 2018 Reliability Project Status Report as of October 31, 2018
2018 10 31 UD-17-04 ENO Transm Letter & Quanta Assessment
2018 09 07 UD-17-04 ENO Letter to CM Moreno and Council re Quanta Technology
2018 07 30 UD-17-04 ENO Bi-Monthly Report on Customer Outages for April 1, 2018- May 31, 2018
2018 07 05 UD-17-04 ENO Root Cause Analysis- Outage Causes Trend Exhibit 3
2018 07 05 UD-17-04 ENO Revised Reliability Plan Re. R-18-98
2018 07 05 UD-17-04 ENO Remediation Plan for FOCUS & BACKBONE devices Exhibit 4
2018 07 05 UD-17-04 ENO Reliability Champions Guidebook Exhibit 5
2018 07 05 UD-17-04 ENO Grid Mod Exhibit 2
2018 07 05 UD-17-04 ENO Electric System Reliability Project Exhibit 1
2018 06 06 UD-17-04 ENO Re. Council Resolution R-18-98
2018 06 06 UD-17-04 ENO Outage Cause Analysis – 2013 – Mar 31 2018 Ex, TSP-3
2018 06 06 UD-17-04 ENO Actual Spending Analysis 2016-5/31/18 Ex. TSP-5
2018 06 06 UD-17-04 ENO 2016 Reliaility Blitz Devices 2017 Cis Avoided Ex. TSP-7
2018 06 06 UD-17-04 ENO 2015-2017 SAIDI, SAIFI Analysis Ex, TSP-4
2018 05 31 UD-17-04 ENO Bi-Monthly Report on Outages Feb 1, 2018- March 31, 2018 Cover Letter
2018 05 31 UD-17-04 ENO Bi-Monthly Report on Outages Feb 1, 2018- March 31, 2018
2018 04 30 UD-17-04 ENO Motion to Extend Procedural Schedules Proposed Order
2018 04 12 UD-17-04 ENO’s Re_CNO R-18-98 Discovery Responses
2018 03 14 UD-17-04 ENO Bi-Monthly Outage Report Dec 17-Jan 18
2018 03 14 UD-17-04 ENO Bi-Monthly Outage Analysis Dec 17-Jan 18
2018 01 31 UD-17-04 ENO 2017 SAIDI/SAIFI
2018 01 12 UD-17-04 ENO Bi-Monthly Report on Customer Outages for Oct 1- Nov 30, 2017.xlsx
2017 12 12 UD-17-04 ENO Bi-Monthly Report on Customer Outages for September 30, 2017 Cover Letter
2017 11 10 UD-17-04 ENO Reliability Plan
2017 09 05 UD-17-04 ENO Objection to Intervention Request of LA Resiliency Project
2017 10 05 UD-17-04 GSREIA Petition for Out of Time Intervention
2017 09 11 UD-17-04 LRP Order and Motion to Dismiss P.o.I.
2017 08 25 UD-17-04 Urban Conservancy Petition for Intervention
2017 08 25 UD-17-04 Tulane Canal Neighborhood Ass. Intervention
2017 08 25 UD-17-04 PNAAR Intervention
2017 08 25 UD-17-04 MCNO Petition for Intervention
2017 08 25 UD-17-04 Lower 9th Ward CSED Intervention
2017 08 25 UD-17-04 Lower 9 Resilient Petition for Intervention
2017 08 25 UD-17-04 LA Resiliency Project Petition for Intervention
2017 08 25 UD-17-04 Denise T. Turbinton Petition for Intervention
2017 08 25 UD-17-04 Dawn Hebert Petition for Intervention
2017 08 25 UD-17-04 David Dalia Petition for Intervention
2017 08 25 UD-17-04 Carrollton Riverbend Neighborhood Association Petition for Intervention
2017 08 25 UD-17-04 Algiers Neighborhood Presidents Council Petition for Intervention
2017 08 23 UD-17-04 (MARI) Maple Area Residents Inc. Petition of Intervention
Please feel free to contact the Alliance if you or your organization would like more information regarding the documents provided on this page.