Hurricanes during the 2020-2021 season alone have caused $4.4 billion worth of damages and much of these costs will show up on our bills. This new resilience docket is a great start to planing for a safer, more climate-ready New Orleans.
Stronger poles, hardened lines, and smarter system design can reduce outages and lower long-term storm costs. These investments are necessary, and The Alliance has consistently supported meaningful, well-designed grid hardening that delivers real benefits to the community, especially to those most vulnerable.
Check out the comments and recommendations we have submitted below and get up to speed on the latest on our blog.
Phase 1 of Entergy New Orleans’ (ENO) Resilience Plan was approved by the Council in 2024 and included $100 million for grid hardening investments. So far ENO has completed 14 of the 32 planned resiliency projects approved in Phase 1, with 7 more under construction, and says all 32 will be completed by the year’s end.
At the end of 2025, ENO submitted an application requesting approval from the Council to begin Phase 2 of its plan, asking for an additional $400 million from customers to strengthen the city’s electric grid. ENO’s application to begin Phase 2 is still currently under review by the Council.
No documents yet
2024 07 30 UD-21-03 AAE Letter to CNO
2024 07 24 UD-21-03 AAE 4th Technical Conference Powerpoint.pptx
2024 07 17 UD-21-03 AAE Proposed Resilience Metrics & Enforcement Mechanism Pursuant to R-24-73
2023 07 21 UD-21-03 AAE Final Comments Re. Resilience Proposals
2022 12 07 UD-21-03 AAE Reply Comments
2022 11 07 UD-21-03 AAE Comments
2022 07 01 UD-21-03 AAE Initial Resilience Plan
2022 02 16 UD-21-03 AAE & GNOICC Joint Motion Against ENO’s Motion to Extend Deadline
2025 11 23 UD-21-03 CNO R-25-664 Att. C (Reporting Metrics)
2025 11 23 UD-21-03 CNO R-25-664 Att. B (Resilience Pole Metric)
2025 11 23 UD-21-03 CNO R-25-664 Att. A (Grid Hardening Reporting Reqs)
2025 12 18 UD-21-03 CNO R-25-664 Directing ENO to Implement Resilience Metrics
2025 02 11 UD-21-03 CURO Updated Service List
2024 10 29 UD-21-03 CNO R-24-625 Partially Approving ENO Resilience Plan
2024 10 21 UD-21-03 CURO Updated Service List.docx
2024 08 01 UD-21-03 CURO Updated Service List.docx
2024 07 18 UD-21-03 CURO 4th Tech Conf Agenda.docx
2024 05 22 UD-21-03 CURO Updated Service List.docx
2024 05 09 UD-21-03 CURO Updated Service List.docx
2024 03 05 UD-21-03 CURO Updated Service List.docx
2024 02 22 UD-21-03 CURO R-24-73 Partially Approving ENO Resilience Plan
2024 02 08 UD-21-03 CURO Updated Service List.docx
2024 02 06 UD-21-03 CURO Updated Service List
2023 08 17 UD-21-03 CURO Administrative Record Chart
2023 07 25 UD-21-03 CNO Order Re. PRE Late Comments
2023 07 05 UD-21-03 CURO Updated Service List
2023 05 24 UD-21-03 CURO Updated Service List.docx
2023 05 01 UD-21-03 CNO Approved TNO Late Intervention
2023 04 25 UD-21-03 CNO Order Re. TNO Late Intervention
2023 04 11 UD-21-03 CURO Updated Service List.docx
2023 02 16 UD-21-03 CURO R-23-74 Adopting Procedural Schedule
2023 01 10 UD-21-03 CURO Updated Service List.docx
2022 12 20 UD-21-03 CURO Order Approving APC Late Reply Comments
2022 12 15 UD-21-03 CURO Order Re. APC Late Reply Comments
2022 12 15 UD-21-03 CURO Updated Service List.docx
2022 11 15 UD-21-03 CURO Updated Service List.docx
2022 09 22 UD-21-03 CURO Updated Service List.docx
2022 09 15 UD-21-03 CURO R-22-411 Establishing Procedural Schedule
2022 08 24 UD-21-03 CURO Updated Service List.docx
2022 08 17 UD-21-03 CURO Updated Service List.docx
2022 07 28 UD-21-03 CURO Updated Service List.docx
2022 06 21 UD-21-03 CURO Approved TNO Intervention
2022 06 16 UD-21-03 CURO Updated Service List.docx
2022 06 13 UD-21-03 CURO Order Re. TNO Late Intervention
2022 03 25 UD-21-03 CURO Updated Service List.docx
2022 03 04 UD-21-03 CURO Order Clarifying Commencement of Discovery
2022 03 01 UD-21-03 CURO Order Granting Extension
2022 02 18 UD-21-03 CNO Order Re. ENO Amended Motion
2022 02 18 UD-21-03 CURO Updated Service List.docx
2022 01 18 UD-21-03 CURO Updated Service List.docx
2021 12 16 UD-21-03 CURO Updated Service List.docx
2021 12 07 UD-21-03 CURO Updated Service List.docx
2021 11 22 UD-21-03 CURO Updated Service List.docx
2026 09 14 UD-21-03 ENO Post-Event Rpt Re. Tropical Storm Arthur (Public)
2026 05 15 UD-21-03 ENO Quarterly Accelerated Resilience Program Monitoring Report
2026 02 16 UD-21-03 ENO Quarterly ARP Monitoring Report (Public)
2025 12 19 UD-21-03 ENO Phase 2 Resilience Plan Application & Request for Relief
2025 11 17 UD-21-03 ENO Quarterly Monitoring Report Regarding ARP Pursuant to R-24-625 (Public)
2025 10 31 UD-21-03 ENO Notice & Summary Rider RSHCR & EFRP Pursuant to R-24-625
2025 08 14 UD-21-03 ENO GRIP Project Update Pursuant to R-24-73
2025 02 19 UD-21-03 ENO Ltr Re. GRIP Project Pursuant to R-24-73
2025 02 12 UD-21-03 ENO Letter Regarding GRIP Project Pursuant to R-24-73
2024 12 18 UD-21-03 ENO 2nd Revised Rider RSHCR Filing & Notice Proposed Rider EFRP Rate Adjustment
2024 12 09 UD-21-03 ENO Accelerated Infrastructure Hardening Project List (Public)
2024 11 22 UD-21-03 ENO Resilience & Storm Hardening Cost Recovery Rider Filing
2024 08 01 UD-21-03 ENO GRIP Projects Monitoring Report Pursuant to R-24-73
2024 07 17 UD-21-03 ENO Proposed Resilience Metrics & Reporting Pursuant to R-24-73
2023 07 21 UD-21-03 ENO Final Comments Re. Resilience Proposals
2023 04 17 UD-21-03 ENO Resilience Plan Phase I Amended Application (Public)
2023 04 17 UD-21-03 ENO Resilience Plan Phase I Application (Public)
2022 12 07 UD-21-03 ENO Reply Comments
2022 11 07 UD-21-03 ENO Comments
2022 10 14 UD-21-03 ENO Resiliency Filing Resubmission Exhibits A & B (Public)
2022 07 01 UD-21-03 ENO Resiliency Filing
2022 02 25 UD-21-03 ENO Reply Memorandum
2022 02 17 UD-21-03 ENO Amended Motion to Extend Filing Deadline