How Entergy’s new gas plants will add nearly $15 to your monthly bill

11.24.2026
Utility Regulation
Entergy Louisiana
Consumer Protection
Bills & Economics

While the enormous build out of power infrastructure to energize Meta’s Hyperion data center has captured most of the headlines at the Louisiana Public Service Commission in recent months, Entergy has another $4.1 Billion ask: two more 750 MW gas plants. Early this year, Entergy filed an application to build these two new plants, one at Waterford campus in St. Charles Parish, and one in Calcasieu Parish.

The Waterford campus is already home to gas and nuclear facilities and another new gas plant already under construction to serve Meta, which was approved in August 2025 (more on that later). The Westlake plant would be sited in the highly industrialized area near another relatively new gas power station called the “Lake Charles Power Station”.

How Entergy's new gas plants will add nearly $15 to your monthly bill

Before we go any further, it is important to know that Entergy says this package of two new gas plants will cost Louisiana residents roughly $15 per month for a 1000 kwh bill. Average Louisiana residents use more like 1500 kwh monthly and even more than that in the summer time, meaning these two plants will actually pack a bigger punch, raising bills 10% over today’s 1000 kwh bill when the facilities come online. 

Entergy’s application makes it clear they want these facilities to serve new industrial energy demand in southeast and southwest Louisiana, including specifically Hyundai’s steel plant, CF Industry, and Woodside LNG. A couple of weeks ago the LPSC held an evidentiary hearing, putting new testimony into the record to give the Administrative Law Judge (ALJ) and the Commissioners the information they need to approve or deny these plants. During that hearing, Entergy’s witnesses insisted that there was little risk to ratepayers because the utility was confident that the industrial demand they expect will show up. Their confidence apparently stems not from analysis or risk assessments, but from relationships they have with industrial customers. The problem we see with this is, whether these three large energy users show up or not, these two plants still represent at least $15 per month on household bills for Entergy Louisiana customers. 

The other problem we see is that the other gas plant the Commission approved last year for Waterford has already cost Entergy more than $676 Million more than they had projected when the Commission approved it. That’s more than a 62% increase. When Entergy asked last year to build this plant (and two others for Meta) the LPSC did not put a cap on how much the total power plant could cost. This means that unless the Commission conducts a prudence review, and doesn’t allow Entergy to recover all of those costs, Entergy will be able to pass the more than half a billion dollars on to customers including Meta, residents, and small mom and pop shops. And now they want to build another plant at that site. When asked at the hearing if Entergy would be willing to accept a “cap” on the cost to limit risk to ratepayers, the utility said they should be allowed to recover all prudent costs spent… even overages.

Around the same time last year when the LPSC was deciding on the first tranche of Meta build out, the Texas PUC approved some resources for Entergy and put a limit on how much the utility costs could run over before shareholders had to foot the bill. We think the Louisiana Commission needs to take up this tactic to ensure ratepayers don’t wind up being sold a bill of goods, and then getting an unexpected bill on top of it. 

One thing that is different about this proceeding from the Meta-related deal is that we currently expect to receive a recommendation from the Commission’s Administrative Law Judge. We expect that a filing and recommendation from the ALJ would come sometime in January, but Entergy is pressuring the Commission to vote on this pair of plants in December. We think it is critical that the Commission wait for an ALJ recommendation, and not force a vote through under a lame duck Commission. $15 a month matters.