May 25 Outage After Action Report

11.24.2025
Reliability & Resilience
Utility Regulation
Louisiana Public Service Commission
New Orleans City Council
Entergy Louisiana
Consumer Protection
Transmission

What Caused the May 25 Blackout?

The LPSC Staff, Entergy Louisiana (ELL) and MISO have each  released ‘After-Action Reports’ that take a deep-dive and investigate what caused the May 25, 2025 blackout, and to provide recommendations to avoid a similar type of blackout from happening again.

Below is a high-level summary of the reports.

Never heard of MISO before? Get up to speed

What caused my power to go out?

1. Too many power plants were offline from planned and unplanned power plant outages. 50% of the generation in our area was unavailable.

Details about power plant outages

ELL’s River Bend nuclear power plant was subject to an unplanned outage on May 21. The outage was a result of a leak in the reactor’s cooling system. The leak was repaired and River Bend returned to service on May 26.

ELL’s Little Gypsy 3 gas power plant also suffered an unplanned outage. The outage began on April 1 and was due to turbine vibration issues.

Washington Parish Energy Center Unit 2 gas power plant experienced an unplanned outage in the early afternoon of May 25. It returned to service and reached full output about fifteen minutes after the May 25 outage and load shed event began.

Because of this unit’s location relative to the transmission constraint, its outage did not contribute to the blackout.

Several non-Entergy generators in southeast and south-central Louisiana also were experiencing unplanned outages on May 25.

 2. A major transmission line was out of service. That line usually moves power from southwest Louisiana to southeast Louisiana.

More on the Nelson–Richard transmission line

The Nelson–Richard 500kV transmission line was unable to operate on May 25. This was the result of damage from a tornado in March. This line moves power from southwest Louisiana to southeast Louisiana. The line was fully repaired and returned to service on May 27, 2025. According to Entergy no other planned or unplanned transmission outages contributed to the blackout.

3. Short timelines to act, limited communication, and a transmission outage designation unique to MISO left operators and utilities with limited time to manage the situation.

MISO is the only transmission operator with a temporary IROL designation

MISO is the only transmission operator with a temporary Interconnection Reliability Operating Limit (IROL) designation. A temporary IROL is a specific, urgent reliability designation used by MISO when a transmission line or system condition is temporarily limited, and exceeding that limit could lead to a widespread power outage, system instability, or cascading outages and physical grid damage. The unique temporary IROL designation results in a very limited amount of time to communicate between grid-operators, utilities and regulators.

Recommendations from the After-Action Report

The below recommendations are a high level summary of the three after-action reports prepared by Entergy Louisiana, MISO, and Public Service Commission staff/advisors (LPSC Staff Report, Entergy Louisiana After-Action Report, MISO After-Action Report).

  1. Improve How Emergency Grid Problems are Handled (IROL Events)
  2. Fix Load Pockets & Build More Regional Transmission Capacity
  3. Better Modeling & Grid Studies

Keep reading for more specifics on these recommendations.

System & Risk Planning

  • Develop a better understanding of how “rare event” scenarios (like May 25) might happen again, and plan for them proactively rather than only reacting when they occur.
  • Improve Emergency Procedures

Improve Communications

Improve communications between local utilities, MISO, regulators, and the public during a transmission emergency. 

  • Update how MISO communicates with local utilities, regulators, and the public during a transmission emergency. (Right now, there’s a gap.)
  • Increase transparency around what’s being done to prevent future “IROL-type” events, especially in regions that are known to be at risk.
  • Work with stakeholders about the way MISO uses certain temporary grid designations. Participate in table-top exercises to be prepared if a similar situation happens again.

Long-Term Regional Transmission Planning

Regulators in Louisiana, Arkansas, Mississippi and Texas and MISO must work together to develop regional plans for a grid that benefits everyone. 

The Alliance’s Thoughts

Our regulators must push utilities to fix load pockets by working regionally to expand transmission capacity and develop a regional, modern power grid. One way to do this is by finding solutions to and fixing the Amite South and Downstream of Gypsy (DSG) load pocket by planning in coordination with regional neighbors, and building more transmission. 

MISO will begin a Load Pocket Risk Assessment in 2026. This assessment will examine the needs and solutions to potentially fix the load pocket issues in southeast Louisiana, where the May 25 blackout happened.

The Alliance will monitor the MISO Load Pocket Risk Assessment and will keep you updated. Stay tuned!
Related News
Proposal for Floating Methane Gas Power Plant Defeated in Louisiana
11.13.2025
Utility Regulation
New Ways For Entergy Louisiana Customers To Save
10.19.2025
Utility Regulation
Entergy New Orleans Tries to Take Credit for Clean Energy It Didn’t Create
10.13.2025
Utility Regulation, Renewable Energy
Watch Your Gas Bill: A New Utility, A New Fee You May Not Owe
10.07.2025
Utility Regulation
October 11: Your Wallet is On the Ballot
09.27.2025
Utility Regulation
Instant Grid Info at Your Finger Tips
09.02.2025
Utility Regulation, Renewable Energy
Surprising Return of Energy Efficiency Means Great Things to Come for LA
08.29.2025
Utility Regulation